House Raising (Finished)
And this is it...!!! House Raising DONE (15/4/25)We finally got there.. and now the rain has stopped... and that's good!Stash, Josh and Nicko finished off the house raising part (bar…
And this is it...!!! House Raising DONE (15/4/25)We finally got there.. and now the rain has stopped... and that's good!Stash, Josh and Nicko finished off the house raising part (bar…
And this is it...!!! House Raising DONE (14/4/25)And of course it rained again, and the neighbour parked her little car in our driveway, retaining wall backs caved in with lots…
The New View (12/4/25)Today both Michelle and I climbed up the extension ladder (4.2 mtrs off the ground) to check out the new view. Not bad we must say.
Legs Attached and Steel Partly Up (11/4/25)What a day... OzBuild rocked up at 730 to deliver the LVLs and SructaFlor and nailing plates which was fantastic. At 745 Rocky from…
Legs in situ (8/4/25)This morning the new legs where surrounded by concrete with lots of starter bars to later tie into the garage slab. Daz also cleaned up the concrete…
The new legs have arrived (7/4/25)Today the new steel posts have been put into position and are ready to be concreted in. The front four posts have been upgraded to…
Daz is back, yes! (4/4/25)Great to see Daz back at 630AM to dig our 12x piers which all got done in one day. All but 2 piers are at least…
She is in her final position Mark the day... lots of photos... the house is in her final new position, the front verandah is now 4.2mtrs from the ground, about 2.7mtrs…
Finally, she has been moved!!! (1/4/25)No joke, the house has actually been moved today, yes! It's been a massive long day for the Steel crew who worked super hard to…
Sliding and Straightening Another rainy day but the Steele crew rocked up and worked hard to slide and straighten the house into position, mega effort. Posts marked ready to be welded…
Finally, core earthworks done! (27/3/25)After 21 days of digging and 70 big truck loads of dirt we are now down to cut level so the house can finally be moved.…
12 more truck loads out today (26/3/25)0630 till 4PM, nearly there, got RW blocks delivered, tomorrow 2x truck loads and moving the house finally, fingers crossed the RAIN stays away.Big…
Getting close now (25/3/25)Dazz came back and worked hard cutting through rock to get to slab cut level. Getting very close now. Another big mount of rock and dirt waiting…
12 more Truck Loads of dirt (24/3/25)Dazz came back and we had 3 10-tonnersto moving out dirt, starting to look a little bit different now. Back again tomorrow and maybe…
Back into the dirt (21/3/25)Dazz and Neil came back to move more dirt and start cutting the lower wall. Another 100 cubic mtrs to come out. Dazz back tomorrow (Sat)…
Steele and Steel (18/3/25)Another day with the excellent Steele crew putting in steel under the house and pouring concrete into the extension piers with MiniPump. Tomorrow the big PFC380 is…
House is in the Air (17/3/25)The crew came back today and the house has been lifted another half a metre into the air. The Steele team worked hard on hanging…
House is in the Air (14/3/25)Today, 14/3/25 the house has been lifted from her stumps for the first time in 128 years sitting on a few stacks of timber styes.The…
House Raising Prep - RW Footings and House PiersDaz has been working hard again and cut the top section retaining wall footings and the 14 piers. Great progress. The northern…
House Raising Prep - Cyclone DelaysCyclone Alfred finally made it to Brisbane. The day before it hits, we got the house extension piers marked with Jack from Steele. The site…
House Raising PrepHad to go into hospital for an angiogram because of a recent discovery of heart disease. No fun, super stressful and of course no progress on site. Took…
House Raising PrepFriday again, finally... Yet another day of digging.
House Raising PrepAnother day of digging, it's starting to look like a quarry a bit, lota of hammering typical Paddington rock.
House Raising Prep (Day 2)Dazz is back into it, cutting more soil and rocks, made some great progress today. Filled up four big tippers which looked like it didn't make…
House Raising PrepGot an early call that there were machine breakdowns so no work will be done today,On the positive side, our surveyor has set all surveying pins ready for…
House Raising PrepUnexpectedly I got a call from Shane that there was a cancellation of another client's job and that we could get started on cutting the site early. Yes…
Raising and Sliding and RestumpingSome (if not most) people find this phase scary and daunting and it sure can be exactly that. But there are ways to minimise the stress…