The Crane
The Crane (30/4/25)Sometimes getting in a helper is useful. We had a 7mtrs double-welded 300PFC as well as 20 300x45 LVLs at 12 metres to all go to the back…
The Crane (30/4/25)Sometimes getting in a helper is useful. We had a 7mtrs double-welded 300PFC as well as 20 300x45 LVLs at 12 metres to all go to the back…
Framing (day 2 - 23/4/25)Huge progress by Brad and Sons. Tamati and Joe from Platinum Concreting also worked hard to get the steel footings ready for pouring tomorrow. And yes,…
Framing (day 1 - 22/4/25)Finally the framing has started, six packs of 6000x90x35 MPG12s delivered by Paul from OzBuild. The steel for the RW Phase 2 also arrived today. Brad…
Progress and Crews (16 & 17 April 25)Today(16th) the LVLs were delivered by Paul from OzBuild (again) and luckily Daz and the 5-tonner were on site to help getting them…
Today we finished RW Phase 1, core-filled and super straight and strong. Magnificent job by both Aiden and Lucas from Mancini Masonry and Chris from Pump-Eez.
Aiden and Lucas from Mancini Masonry work hard today and built a truly perfect retaining wall, so impressive. One more small section to build (need more blocks) and the core…
Retaining Walls (Phase 1) Today 24/3/25 was wet early in the morning but we got the job done and the footing steel signed off by our engineer. The footings for RW…
Retaining Walls We found a very skilled and nice bricklayer called Aiden Mancini. This work will hopefully start next week 1/4/25.We have split the RW work into three phases, being:RW Phase…