Retaining Walls (Phase 1)

 

Today 24/3/25 was wet early in the morning but we got the job done and the footing steel signed off by our engineer. The footings for RW Phase 1 are being poured tomorrow.

…and it was poured.. Tamati and Joey put in a massive day, several Boral trucks later the RW Phase 1 footings were done, nice work.