Weight lifting day… manually lifted more than 4,000kg of timber into and again out of the trailer dumping it at Ferny Grove Refuse Centre while it was bucketing down with rain. Had to pay $96. Prepared for dumping the rest tomorrow. Then after lunch starting to pull down some of the floors and “supporting” structures below.
Thank you Joey for helping me to complete the Form 1 (so he can lodge his Form 7) and for capping off the water and gas. PS. Our soil report has a classification of Class S as well as Class P but there are no trees on the property (and hence no articulation report was done), I should have picked up on this ages ago, now it’s going back to Morgan Engineering to discuss and rectify,… but we will get there.
PS. I will save you a section of 1500*2400 Adrian ;-).