May has been and still is an absolute mad month and we still have a few days to go before June (and more rain) arrives. The fact that I haven’t updated the posts is evidence of how busy we have been and got soooooooooo much done… and the month is not over yet. Needless to say that the money is flying out the door pretty quick smart but the results are obvious. And given all the rain we’ve done pretty well I reckon, thanks to all the subbies for putting in another mammoth effort.

Here is a list of the May 2025 deliverables:

General
House Raising completed
All new glass installed (windows and doors)
Scaffold installed
Finalised kitchen design
Trusses built
Plumbing rough-in started
Electricals rough-in started
RW3 cut and footings poured
1/2 internal VJs delivered

Top Floor
All chamfer boards on
All windows installed
2x big ones lifted
All framing completed
Trusses installed

First Floor
All chamfer boards on
All framing
Verandah demolished and rebuilt (incl. waterproofing)
Large steel beam installed (with The Crane)

Ground Floor
Garage slab finished (incl. plumbing & termite protection installed)
Retaining Wall RW2 up
Waterproofed RW1 and RW2
Neigbbouring RW cut

Planned for the rest of May
Roof prepped
Get inside ready for rough-in and VJ install